Before You Break Ground: Environmental Permitting Considerations for Development Projects

Businesses that deal with construction, real estate and utilities frequently engage in land development activities. Prior to starting construction, businesses should consider whether their proposed development may trigger permitting or other requirements. This could include an Erosion and Sedimentation Permit, an Encroachment Permit, a National Pollution Discharge Elimination System (NPDES) Permit, a wetland delineation, a Soil Plan or a fill determination.

Developers also must be aware of the risk of hitting utility lines during construction. All developers must call 811 at least three business days prior to breaking ground to determine whether there are any utility lines in the area. This can reduce safety risks and save time and money. If a developer hits a utility line during construction and failed to call before construction, the Pennsylvania Public Utility Commission can require payment of monetary fines.

Consider This

Development activities can cause erosion and sediment pollution, which can degrade water quality and harm aquatic organisms. Development activities that remove natural buffers to runoff, such as the removal of trees and the addition of impervious surfaces, can increase stormwater runoff. Excess stormwater can exacerbate flooding and increase erosion. Additionally, development activities can encroach upon or alter the path of an existing waterway or enlarge or diminish that waterway. The Pennsylvania Department of Environmental Protection (PADEP) attempts to minimize erosion and sedimentation, and encroachments through Chapter 102 and Chapter 105 permits, respectively.

Best Management Practices (BMPs) are required during all development activities to reduce erosion and sedimentation during construction. Examples of BMPs include silt fences, silt socks, and turbidity barriers. Development activities that include an earth disturbance equal to or greater than 5,000 square feet require an Erosion and Sedimentation Plan pursuant to Chapter 102. An Erosion and Sedimentation Plan includes a description of the area, the proposed earth disturbance, site plans, and Post Construction Stormwater Management (PCSM) the developer will utilize.

Earth disturbances greater than one acre generally also require a National Pollution Discharge Elimination System (NPDES) stormwater permit. NPDES permits govern the discharge of pollutants into a waterbody. The NPDES permit application will require an Erosion and Sedimentation Plan and a stormwater management plan. The PADEP administers the NPDES permit program in Pennsylvania. The NPDES permit creates pollution limits that are designed to protect the waterbody. For development activities specifically, a NPDES permit will limit the stormwater discharge that can occur from the permitted site.

In Pennsylvania, the PADEP has delegated much of its authority to issue Chapter 102, Chapter 105 and NPDES permits to the county conservation districts. Therefore, those seeking permits must typically work with their local county conservation district to obtain the applicable permits.

Furthermore

If the site contains wetlands or is located adjacent to a waterway (stream, river, creek) or a waterbody (bay or lake), the earth disturbance may also require a PADEP Chapter 105 Encroachment permit. Chapter 105 Encroachment permits are required for any activity that may encroach upon or impact a waterway or waterbody. If wetlands are located in the area, the developer may need to complete a wetland delineation to determine if a wetlands is likely to be impacted or encroached upon. A wetland delineation is the process of identifying, characterizing, and mapping wetlands on a site.

An additional consideration is whether development activities will generate fill on the site. If no fill is generated on site or the fill is known to be clean fill, then no additional permits are required. Alternatively, if the fill is regulated fill, it can be used on the site without further restrictions. Any soils that are contaminated beyond regulated fill standards must be disposed of offsite.

While these permits and plans create additional requirements during development, developers who get ahead of these requirements will help themselves in the long run. Failing to obtain the required permits can disrupt construction in the middle of a project, which can create a multitude of problems. Additionally, while many of these plans are required upfront, the county conservation districts and PADEP generally are amenable to changes throughout the construction process.